(75)is the process of obtaining the stakeholders’ formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
A.Project acceptance
B.Scope verification
C.Scope definition
D.WBS Creation

【答案】B
【解析】
范围验证是指获取项目干系人对已完成的项目范围的正式任何的过程。验证范围包括了评审可交付物的工作成果,以确定它们均已令人满意地完成