高项题库-2005上-综合知识-第74题

高项题库-2005上-综合知识第74题(单选题)
(74)are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
A.Controls
B.Baselines
C.Project stakeholders
D.Project managers

【答案】C
【解析】
项目干系人是积极参与到项目中,或其利益可能会受项目执行或完成结果影响的个人或组织;他们可能会对项目及其结果施加影响。