高项题库-2015下-综合知识-第74题

高项题库-2015下-综合知识第74题(单选题)
Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and( )
A.fast tracking
B.what-if scenario analysis
C.resource leveling
D.critical chain method

【答案】A
【解析】
进度压缩技术包括快速跟进