中项题库-2012上-综合知识第73题(单选题)
Project manager believes that modifying the project scop may provide added value for the customer.The project manager should(73).
A.change the scope baseline
B.contact the customer to determine if the change adds value
C.call a meeting of the change control board
D.change the project’s objectives
【答案】B
【解析】
项目经理相信范围变更会给客户带来更多的价值,项目经理应该先联系客户以确认变更是否能够带来价值(contact the customer to determine if ?the change adds value)