中项题库-2013上-综合知识第74题(单选题)
All of followings should be done by the project manager during project control except ( ).
A.Determine that a change has occurred
B.Ensure that a change is agreed
C.Make sure all changes are approved by management
D.Manage changes as they occur
【答案】C
【解析】
下列哪项是范围确认的重要输入( )。
A、工作成果
B、历史信息
C、正式的认可
D、变更申请