高项题库-2010上-综合知识第71题(单选题)
(71)assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality.
A.Quantitative Risk Analysis
B.Qualitative Risk Analysis
C.Enterprise Environmengtal Factors
D.Risk Management Plan
【答案】B
【解析】
定性风险分析(Qualitative Risk Analysis)利用分析发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围和质量的风险承受度水平),对已识别风险进行优先级的评估。