高项题库-2013下-综合知识-第74题

高项题库-2013下-综合知识第74题(单选题)
A()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.
A.gantt chart
B.project histogram
C.milestone chart
D.project flowchart

【答案】A
【解析】
A是甘特图,B是项目直方图,C是里程碑图,D是项目流程图