高项题库-2019上-综合知识-第73题

高项题库-2019上-综合知识第73题(单选题)
(73)are those costs that cannot be directly traced to a specific project and therefore will be accumulated and allocated equitably over multiple projects by some approved and documented accounting procedure.
A.Direct costs
B.Operation costs
C.Indirect costs
D.Implement costs

【答案】C
【解析】
()这些费用是否无法直接追溯到某一具体项目,因此将由某些经核准和有文件记录的会计程序在多个项目中加以累积和公平分配。
A、直接费用
B、业务费用
C、间接费用
D、执行成本