高项题库-2008下-综合知识第72题(单选题)
Project work packages are typically decomposed into smaller componentscalled activities to provide a basis for(72), scheduling, executing, and monitoring and controlling the project work.
A.reviewing
B.estimating
C.auditing
D.expecting
【答案】B
【解析】
把项目工作包分解成更小的称为活动的单元,为估算、进度安排、项目执行、项目监控提供了基础。