There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, Some other strategies are suggested to deal with risks with potentially positive impacts.(74)is a risk response strategy that may be adopted for either threats or opportunities.
A.share
B.Mitigate
C.Transfer
D.Acceptance

【答案】D
【解析】
一部分策略用于应对威胁或可能给项目目标带来消极影响的风险;另一部分策略用于处理对项目目标有潜在积极影响的风险,接受(Acceptance)是一个既可用来应对威胁,也可用来应对机会的风险应对策略。
A选项:风险;B选项:减轻;C选项:转移