中项题库-2011上-综合知识-第74题

中项题库-2011上-综合知识第74题(单选题)
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project ’ s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that (74).
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date

【答案】B
【解析】
挣值分析技术是一种综合了范围、成本、进度指标的常用绩效测量方法。它帮助项目团队评价项目绩效。如果一个项目的进度绩效指数SPI值小于1,意味着()。
A.进度超前B.进度滞后 ?C成本超支 ? ?D成本结余
根据《系统集成项目管理工程师教程》(全国计算机专业技术资格考试办公室组编)第9.5.3小节的内容可知,SPI值小于1表示实际进度落后于计划进度。
因此,正确答案应选B。