The project manager has just completed a business process improvement project. The project has been deemed a failure by management primarily because it was completed three weeks late. In the project charter, the sponsor imposed an admittedly aggressive de

作者:admin  阅读量:2999  时间:1970-01-01
The project manager has just completed a business process improvement project. The project has been deemed a failure by management primarily because it was completed three weeks late. In the project charter, the sponsor imposed an admittedly aggressive deadline. The project manager claims the timeline was unrealistic from the start, and he and the team did everything possible to achieve the required timeline. An unrealistic schedule is the fault of the: A:Customer B:Project manager C:Sponsor D:Team 答案及解析参见【象网PMP】微信小程序,可对试题关键字进行全文检索。也可在象网PMP备考群提问