You are working on the performance reporting for the project you are managing. Schedule performance is the top constraint. As you are gathering the data, you need information for the formulas that you will be reporting on. Which of the following represent

作者:admin  阅读量:3101  时间:1970-01-01
You are working on the performance reporting for the project you are managing. Schedule performance is the top constraint. As you are gathering the data, you need information for the formulas that you will be reporting on. Which of the following represents the value of work actually completed? A:Estimate to complete B:Earned value C:Planned value D:Actual cost 答案及解析参见【象网PMP】微信小程序,可对试题关键字进行全文检索。也可在象网PMP备考群提问