Based on the chart, while completing the project, a team member tells you the team forgot something during planning. Activity F needs the results of activity E before it can begin. Taking this new dependency into account, what would be the effect on the p

作者:admin  阅读量:1630  时间:1970-01-01
Based on the chart, while completing the project, a team member tells you the team forgot something during planning. Activity F needs the results of activity E before it can begin. Taking this new dependency into account, what would be the effect on the project? A:It would delay activity F. B:It would increase the critical path. C:There would be no effect. D:Communication would be more complex. 答案及解析参见【象网PMP】微信小程序,可对试题关键字进行全文检索。也可在象网PMP备考群提问